The company proposing a massive data center campus near Broadview is asking NorthWestern Energy to connect it to the grid at up to 7,235 megawatts — seven times the roughly 1,000 MW it originally announced and about 10 times the entire power load NorthWestern currently serves across all of Montana.

What this means for you
MontanaMontana ratepayers and rural communities bear the most direct stake: Quantica's own-generation claim is the main argument against NorthWestern rate increases, but that commitment is not yet locked in by any filed agreement, and critics are unconvinced. The project's scale — if it materializes — would represent one of the largest single infrastructure investments in state history.
Yellowstone CountyThe proposed 5,000-acre campus sits about three miles south of Broadview. Local residents have already organized public opposition over water and electricity concerns, and DEQ permitting is the next formal proceeding in the county.
Watch nextMontana DEQ permit proceedings for the Broadview campus are ongoing; no public comment deadline was specified in the source material. Watch for NorthWestern Energy's formal response to the 7,235 MW interconnection request.

Quantica Infrastructure disclosed the expanded interconnection request Wednesday in a news release, framing it as a planning move rather than a firm commitment. Company officials said the figure covers the full potential buildout, including renewables, firming generation, and battery storage, and that the campus would not necessarily consume all of that capacity.

"By investing in additional capacity now, we plan to address what we're seeing in terms of power demand from data center companies," CEO John Chesser said in a written statement. "This expansion significantly increases our total investment in Montana, and the additional power capacity would result in even more economic opportunity, construction jobs over several years, and strengthen the State's power grid."

Quantica has said it intends to generate its own power on-site rather than draw heavily from NorthWestern's existing supply — a point the company says would protect current ratepayers from cost increases. The project, known as Big Sky Digital Infrastructure, would sit on 5,000 acres by a substation roughly three miles south of Broadview, a small community in Yellowstone County southeast of Billings.

The company is working with the Montana Department of Environmental Quality on permits for the campus. Firming power sources under consideration include natural gas, geothermal, and other options. Officials said they hope to bring the first building online in 2029. No tenants have been announced.

The scale of the request is drawing scrutiny. Opponents — who turned out roughly 130 strong at a January community meeting in Broadview — have pressed for more transparency from the developer and raised concerns about rising electricity rates and groundwater use, particularly for cooling systems.

"They need to come here in a way that does not harm those of us who already live here," Anne Hedges, executive director of the Montana Environmental Information Center, said at that meeting. "Doesn't increase our electricity bills. Doesn't harm our water resources. Doesn't cause contamination of water."

Data center development has accelerated across Montana over the past year. Separate proposals have surfaced in Butte and in Bonner, near Missoula. A related legal dispute — a Montana businessman's lawsuit alleging Quantica stole a competing AI data center deal in Broadview — is also pending, adding another layer of uncertainty to the project's path forward.

NorthWestern Energy has not publicly stated a timeline for acting on the interconnection request. DEQ permit proceedings are ongoing.