BILLINGS — The developer behind a proposed 5,000-acre energy and data center campus near Broadview says the project will draw 20,000 gallons of water per day once fully operational — and that its design specifically avoids competing with the wells that area ranchers and farmers depend on.

What this means for you
Montana:A 5,000-acre data center drawing from a deep aquifer in Yellowstone County raises legitimate water-rights questions in an agricultural region. The company's claim that the Madison and Eagle aquifers are not hydraulically connected is central to its case that neighbors' wells are safe — state DEQ and DNRC oversight will be the mechanism for testing that claim.
Yellowstone County:Area ranchers and domestic well users draw from the shallower Eagle Aquifer. The developer says its deep Madison well is hydraulically isolated from that formation, but the claim has not yet been independently verified by state regulators in any publicly released finding.
Broadview:The rural community has been actively divided over the project, with thousands of signatures submitted — and then rejected on procedural grounds — seeking a public vote on whether to allow the campus to proceed.
Watch next:Montana Public Service Commission docket on Quantica's 7,235 MW grid interconnection application — check PSC docket filings for hearing dates and public comment periods.

Quantica, which is developing the Big Sky Campus in Yellowstone County, announced Monday that the project will use closed-loop cooling technology — a system that continuously recirculates water rather than replacing it, similar in principle to a car radiator. The company says that design keeps water consumption well below what an open-loop or evaporative cooling system would require.

All water will be sourced from the Deep Madison Group Aquifer through a single deep well, tapping the formation at roughly 4,000 to 5,000 feet below the surface. That's approximately 1,300 feet below the shallower Eagle Aquifer, which supplies most area ranchers and domestic well users. Big Sky Digital Infrastructure, which will operate the campus, says the two aquifers are not hydraulically connected, meaning withdrawals from the Madison should not draw down Eagle Aquifer wells above.

"I grew up on a ranch in Montana, so I know what water means here — you don't take it for granted," said Damon Obie, general counsel of Big Sky Digital Infrastructure. "We designed the Big Sky Campus to use minimal water and to source it deep underground, away from the wells our neighbors rely on."

During peak construction, water usage is projected to rise to 150,000 gallons per day before dropping back to the 20,000-gallon operational figure.

The announcement comes as the project faces significant local scrutiny. Yellowstone County commissioners earlier rejected thousands of signatures gathered by residents seeking a public vote on the data center, after organizers missed a filing deadline following an incorrect date provided by county officials. Supporters of a public vote have said they intend to keep pursuing that path.

The Big Sky Campus is designed to operate at 1,100 megawatts of power. Quantica has separately applied to the Montana Public Service Commission for a grid interconnection capacity of 7,235 megawatts — a figure that reflects the project's potential long-term buildout, not its initial operating load. The company has also been evaluating natural gas generation as a power source for the campus.

Quantica says all water usage will comply with Montana Department of Environmental Quality and Department of Natural Resources and Conservation requirements. The company added that it is in early discussions about potentially making water available to surrounding farms and ranches on a long-term basis, though no specifics or commitments have been announced.

This report is based on coverage by KTVQ-Billings (MTN News).