A Las Vegas-based artificial intelligence and Bitcoin mining company says it has received a formal power commitment from a Montana rural electric cooperative, opening the door to a roughly 12-fold increase in capacity at one of its eastern Montana sites.

Hyperscale Data, Inc. (NYSE American: GPUS) announced Tuesday that its subsidiary BNI Montana, LLC received a "will serve" letter from the Lower Yellowstone Rural Electric Cooperative. The letter indicates that up to approximately 125 additional megawatts of power may be available at one of the company's two Montana facilities — the one that currently runs about 10 megawatts supporting Bitcoin mining operations.

The second Montana location, situated roughly 15 miles away, also operates about 10 megawatts. Hyperscale Data said it has not yet conducted a load study on that second site but is considering one.

**What the letter actually means — and what it doesn't**

A utility "will serve" determination is a meaningful step, but it is not a construction commitment or a guarantee of power delivery. The letter comes with a substantial list of conditions: engineering studies, transmission and distribution upgrades, interconnection requirements, regulatory approvals, construction milestones, and commercial arrangements still ahead. The company acknowledged in its announcement that no estimates or timelines for the required improvements have been set — except that one necessary transmission line already has a completion target of 2031.

That 2031 date for a single transmission line underscores the long runway involved. Hyperscale Data said it has decided to move to the "next phase of evaluation" based on the letter's terms, stopping short of announcing construction plans or capital commitments.

**The company's Montana strategy**

Hyperscale Data acquired its Montana land leases in February 2023. Executive Chairman Milton "Todd" Ault III called the utility determination "a significant milestone" and said the company views the state as a long-term platform for power-intensive infrastructure spanning Bitcoin mining, AI computing, and cloud services.

"While substantial work remains ahead and there can be no assurance regarding the ultimate outcome, we have decided to move this project to the next level," Ault said in the announcement.

The company separately noted a major contract at a different campus: a subsidiary recently executed a long-term agreement tied to its Michigan AI data center that, if fully performed, could represent up to approximately $3.0 billion in value over 20 years.

That Michigan deal is unrelated to the Montana sites but illustrates the scale of infrastructure contracts Hyperscale Data is pursuing across its portfolio.