# Quantica says Broadview data center will draw from deep aquifer, use 20,000 gallons daily at full build
- URL: https://www.the406.news/quantica-says-broadview-data-center-will-draw-from-deep-aquifer-use-20-000-gallons-daily-at-full-build/
- Published: 2026-10-04T16:52:10.000Z
- Updated: 2026-10-04T16:52:10.000Z
- Description: The developer behind the proposed 1,100 MW Big Sky Campus in Yellowstone County released water usage projections Monday, saying closed-loop cooling and a deep Madison Aquifer well will protect neighboring ranch and farm wells.
- Author: Samuel Von Worthington
- Tags: Technology, #zone-billings, #zone-statewide, #ai-assisted, #bridger-edit, #dedupe-e6abccf23c8b9e7f

BILLINGS — Quantica, the developer behind the proposed 5,000-acre Big Sky Campus data center near Broadview, says the facility will draw 20,000 gallons of water per day once fully operational — and that the design specifically avoids the shallower aquifer that neighboring ranchers and farmers rely on.

What this means for you

MontanaA 5,000-acre, 1,100 MW data center in Yellowstone County would represent one of the largest energy and infrastructure investments in Montana's history. Water sourcing from the Deep Madison Aquifer — if the hydraulic separation from the shallower Eagle Aquifer holds — could limit impact on agricultural wells, but that claim has not been independently verified by state agencies in public documents yet.

Yellowstone CountyBroadview-area ranchers and farmers draw from the Eagle Aquifer. Quantica says its deep Madison well is hydraulically isolated from it, but independent aquifer analysis through the DNRC review process will be the key test of that claim for local water-rights holders.

Watch nextMontana Public Service Commission docket on Quantica's 7,235 MW grid-connection application — track at psc.mt.gov for hearing dates and public comment windows.

The company announced Monday that it plans to source all water from the Deep Madison Group Aquifer, reached through a well drilled roughly 4,000 to 5,000 feet below ground — about 1,300 feet below the Eagle Aquifer, which serves most local agricultural users. Officials at Big Sky Digital Infrastructure, the entity that will operate the campus, said the two aquifers are not hydraulically connected, meaning withdrawals from the Madison should not affect Eagle Aquifer wells.

The406.news has not independently verified the hydraulic separation claim; it rests on the company's own characterization. Readers with water rights in the Broadview area may want to track the project's Department of Natural Resources and Conservation review for any independent aquifer analysis.

The campus is designed to use closed-loop cooling — a system that continuously recirculates water rather than replacing it, similar to how an automobile radiator works. Quantica says the approach minimizes overall consumption compared with evaporative cooling systems used at many large data centers.

Water demand will be considerably higher during construction. The company projects peak usage of 150,000 gallons per day while the campus is being built.

"I grew up on a ranch in Montana, so I know what water means here — you don't take it for granted," said Damon Obie, general counsel of Big Sky Digital Infrastructure. "We designed the Big Sky Campus to use minimal water and to source it deep underground, away from the wells our neighbors rely on."

The Big Sky Campus is proposed at 1,100 megawatts of capacity, though Quantica has applied to the Montana Public Service Commission for a grid-connection capacity of 7,235 megawatts — a figure that suggests the company may be planning for significant future expansion beyond the initial build.

Quantica says it is in the early stages of exploring whether it could make water available to surrounding farms and ranches over the long term. All water use will comply with state law, including requirements from the Department of Environmental Quality and the Department of Natural Resources and Conservation, the company said.

The water announcement comes amid ongoing community friction over the project. Yellowstone County commissioners recently rejected thousands of signatures gathered by residents who sought to put the data center to a public vote; organizers missed the submission deadline after county officials gave them an incorrect date. Residents have continued pursuing referendum options despite that setback.